of Darien Department of Public Works,
2020
Summer Paving Program Press Release
The
Town of Darien paving program for the summer of 2020 is as follows:
STREET NAME
|
FROM
|
TO
|
START MILLING
|
FINISH PAVING
|
Edgerton
Court
|
Edgerton
Street
|
End
|
8/6/20
|
8/11/20
|
Edgerton
Street
|
West
Avenue
|
Middlesex
Road
|
8/6/20
|
8/12/20
|
Hilton
Street
|
West
Avenue
|
End
|
8/7/20
|
8/12/20
|
West
Avenue
|
Brown
Street
|
Edgerton
Street
|
8/7/20
|
8/13/20
|
Noroton
Avenue
|
West
Avenue
|
McGuane Field Entrance
|
8/10/20
|
8/13/20
|
Middlesex
Road
|
Leroy
Avenue
|
Hanson
Road
|
8/11/20
|
8/17/20
|
Leroy
Avenue
|
West
Avenue
|
Middlesex
Road
|
8/12/20
|
8/19/20
|
Half
Mile Road
|
Hollow
Tree Ridge Rd
|
Mansfield
Avenue
|
8/17/20
|
8/20/20
|
Greenwood
Road
|
Camp
Avenue
|
Hoyt
Street
|
8/18/20
|
8/8/20
|
Gardiner
Street
|
Post
Road
|
Linden
Street
|
8/18/20
|
8/24/20
|
Birch
Road
|
Post
Road
|
Sylvan
Road
|
8/20/20
|
8/25/20
|
Locust
Hill Road
|
Old
Kings Hwy South
|
Settlers
Trail
|
8/21/20
|
8/25/20
|
Preparatory work will
precede paving on all of the above roads. Dates listed above include
milling and paving. Road surfaces will have raised structures during
these dates. Please avoid these roads if possible during these times or
use extra caution if you must travel on these roads. The above schedule
is based on favorable weather conditions. Emergency access will be
available at all times. Town of Darien police officers will be present to
direct traffic and assist area residents during construction. Driveway
access will be limited during paving operations. However, no single
driveway should be closed for more than an hour. On street parking will
be suspended during paving operations. Minor traffic delays are
likely. Please plan your travels accordingly. Please call the
Department of Public Works at 656-7346 for further information