Town of Darien Department of Public Works,
2021 Summer Paving Program Press Release
The Town of Darien paving program for the summer of
2021 is as follows:
STREET NAME
|
FROM
|
TO
|
START MILLING
|
FINISH PAVING
|
Chasmar Pond Rd
|
Red Rose Circle
|
Cul de Sac
|
7/26/21
|
7/29/21
|
Red Rose Circle
|
Raymond St
|
Raymond St
|
7/26/21
|
7/30/21
|
Dellwood Rd
|
Maywood Rd
|
Cul de Sac
|
7/27/21
|
7/30/21
|
Maywood Rd
|
Point O’Woods Rd
|
Norwalk City Line
|
7/27/21
|
8/2/21
|
McLaren Rd South
|
McLaren Rd
|
McLaren Rd
|
7/28/21
|
8/2/21
|
McLaren Rd
|
Leroy Ave
|
Mansfield Ave
|
7/29/21
|
8/3/21
|
Middlesex Rd
|
Hanson Rd
|
Ox Ridge Rd
|
7/29/21
|
8/4/21
|
Hecker Ave
|
Noroton Ave
|
Post Rd
|
8/2/21
|
8/5/21
|
West Ave
|
Noroton Ave
|
Post Rd
|
8/3/21
|
8/10/21
|
Phillips La
|
Hoyt St
|
Lake Dr
|
8/9/21
|
8/12/21
|
Lake Dr
|
Hoyt St
|
Phillips La
|
8/10/21
|
8/12/21
|
Heather La
|
Hoyt St
|
Cul de Sac
|
8/11/21
|
8/13/21
|
Camp Ave
|
Hoyt St
|
Jackson Pl
|
8/12/21
|
8/13/21
|
Hollow Tree
Ridge Rd
|
Crooked Mile Rd
|
New Canaan Town Line
|
8/12/21
|
8/16/21
|
Preparatory
work will precede paving on all of the above roads. Dates listed above include milling and
paving. Road surfaces will have raised structures
during these dates. Please avoid these
roads if possible during these times or use extra caution if you must travel on
these roads. The above schedule is based
on favorable weather conditions.
Emergency access will be available at all times. Town of Darien police officers will be
present to direct traffic and assist area residents during construction. Driveway access will be limited during paving
operations, however, no single driveway
should be closed for more than an hour.
On street parking will be suspended during paving operations. Minor traffic delays are likely. Please plan your travels accordingly. Please call the Department of Public Works at
656-7346 for further information.